Heliproz is excited to announce that we have finished construction on our new warehouse, retail and manufacturing facility. 20,000 sq.ft. of pure helicopter heaven located on 20 glorious acres just east of Billings, Montana. Plans include a helicopter airfield, lake, clubhouse and picnic area.



Revised artist rendering of our new 20,000 sq.ft. facility in Billings, Montana

New Building Front

This page was starting to take too long to load with all of the photos, so we've archived all the photos from October through March. Click here to view the old photos.



Monday, September 21, 2009: The heli goes up!





Tuesday, August 25, 2009: We have moved in and are now operating out of our new building!


Photos of the HeliProz sign going up.


Truckload of helis moving in, and there's still more! Display helis waiting for their new home . HeliProz logo welcoming you at the entrance.

Starting to set up the retail space. Check out the BIG SCREEN!



The warehouse is filling up fast!





Friday, July 17, 2009: Almost done! We should start moving in on Monday, July 27th. They're finishing up the floors and lighting. Warehouse racks start going up this weekend.

Building 4.30.09   Building 4.30.09 2
 




Wednesday, July 1, 2009: We now have a paved parking lot! Ceilings are done. Interior walls are almost done. It won't be long now.

Building 4.30.09   Building 4.30.09 2
 




Monday, June 15, 2009: New photos of the entrance and retail area for the new building. Crews are finishing the ceilings and the sheet rock is going up.

Building 4.30.09   Building 4.30.09 2




Thursday, May 21, 2009: Progress photos of the outside of the building and of the three interior sections of the building: retail, shipping/warehouse, and machine shop.

Building Entrance
Retail Space
Warehouse
Machine Shop




Tuesday, May 12, 2009: The crews are haulin' now! Floors are in, insulation is done, and walls are going up. Doors, electrical, etc. are all going in. It won't be long now!

Building 4.30.09   Building 4.30.09 2




Thursday, April 30, 2009: They've been able to get a lot of work done this week between snow showers.The front of the building is now enclosed and the windows are in. They continue to pour the floor which is now about 2/3 of the way done. The wall between the machine shop and the warehouse is also going up.

Building 4.30.09   Building 4.30.09 2
 




Friday, April 24, 2009: We actually had a few days of nice weather this week. They were able to get part of the floor poured and more insulation in. They've also framed out most of the front of the building and are ready for the rest of the doors and windows.

Building 4.24.09   Building 4.24.09 2




Friday, April 17, 2009: Not much has happened to the exterior, most of the work has been to the interior. Insulation is going in and electrical conduit is being run. They should start pouring the floor sometime next week.

Building 4.17.09




October 2008 - March 2009 Photos